A dilbo-EE performing NS in Bintulu logs work and after-work activity for project-record purposes and posterity.
Sunday, July 27, 2003
Activities achieved for the week ending 29 Jul 2003
1) Transformer 4201C deenergisation, dielectric tests for old, new & new-postfiltered oil.
2) Installation of Swagelok Fitting and purge spool for N2 inerting after oil-filling.
3) 4201C Gate Pulse Array replacement per contract.
4) Pumpout old oil and fill-up 4201C.
5) Seawater flow startup & energisation of 4201C for overnight no-load test.
6) Deenergisation of 4201C, oil dielectric retest, reenergisation for 75% overnight load test.
7) Relocate scaffolding from 4201C to 4201D
8) Transformer 4201D deenergisation, dielectric tests for old, new & new-postfiltered oil.
9) Installation of Swagelok Fitting and purge spool for N2 inerting after oil-filling.
10) 4201D busbar retorquing and chassis paint touch-up.
11) 4201D Gate Pulse Array replacement per contract.
12) Seawater flow startup & energisation of 4201D for overnight no-load test.
13) Deenergisation of 4201D, oil dielectric retest, reenergisation for 75% overnight load test.
14) 4201A-D electrode scaffolding removal by busbar clamp installation contractor
15) 4201 A-D electrode scaffolding reinstallation by painting contractor
16) Replacement of damaged Exe phone cable in Electrochlorination Plant
17) Replcament of faulty/aged lighting in Electrochlorination Plant
18) Demobilisation of Transformer Oil Change Vendor
19) Attend Clearance Certificate/Permit to Work briefing by HSE and sit for Work Supervisor Test
1) Transformer 4201C deenergisation, dielectric tests for old, new & new-postfiltered oil.
2) Installation of Swagelok Fitting and purge spool for N2 inerting after oil-filling.
3) 4201C Gate Pulse Array replacement per contract.
4) Pumpout old oil and fill-up 4201C.
5) Seawater flow startup & energisation of 4201C for overnight no-load test.
6) Deenergisation of 4201C, oil dielectric retest, reenergisation for 75% overnight load test.
7) Relocate scaffolding from 4201C to 4201D
8) Transformer 4201D deenergisation, dielectric tests for old, new & new-postfiltered oil.
9) Installation of Swagelok Fitting and purge spool for N2 inerting after oil-filling.
10) 4201D busbar retorquing and chassis paint touch-up.
11) 4201D Gate Pulse Array replacement per contract.
12) Seawater flow startup & energisation of 4201D for overnight no-load test.
13) Deenergisation of 4201D, oil dielectric retest, reenergisation for 75% overnight load test.
14) 4201A-D electrode scaffolding removal by busbar clamp installation contractor
15) 4201 A-D electrode scaffolding reinstallation by painting contractor
16) Replacement of damaged Exe phone cable in Electrochlorination Plant
17) Replcament of faulty/aged lighting in Electrochlorination Plant
18) Demobilisation of Transformer Oil Change Vendor
19) Attend Clearance Certificate/Permit to Work briefing by HSE and sit for Work Supervisor Test
Thursday, July 24, 2003
Activities achieved for the week ending Jul22
1) Post overnight noload test oil sampling and dielectric test for electrochlorination transformer 4201A.
2) Overnight loaded test of transformer 4201A; tempaerature check.
3) Deenergisation of transformer 4201B.
4) Filter new oil for transformer 4201B.
5) Replace fuse & thyristor for transformer 4201A after tripping on second night of loaded operation.
6) Install new Gate Pulse Array circuit board for transformer 4201B.
7) Oil sampling and dielectric testing ofr 4201B old, new unfiltered and new filtered oil.
8) Pumpout old oil and fill-up 4201B. Post-fill oil sampling and dielectric test.
9) Re-energise 4201A and energise 4201B for no-load test.
10) Deenergise and reenergise 4201B for load test.
11) Relocate scaffolding from 4201B to 4201C
12) Apply for 4201C deenergisation.
Activities achieved for the week ending Jul15
1) New & higher flowrate transformer oil filter & enclosed 12000L breaker tank arrival onsite, scaffolding-shelter setup, safety inspection.
2) Calibration certificate & manufacturing date trace for both 3rd party & MLNG oil dielectric testers; both testers found overdue for calibration
3) Simultaneous oil degradation-comparison test for both 3rd party & MLNG oil dielectric testers (IEC156 test).
4) Electrochlorination transformer 4201A tap seal repair & tap setting check.
5) Clean/repair corroded contactor at maintenance power receptacle junction box at SS19. Power receptacle used to supply power to the transformer oil filter.
6) Cover transformer oil minor oil spills (caused by sampling) with white sand.
7) Demob of old / contaminated oil filter from electrochlorination area.
8) Uncoupled runs for PM5705A/5B, MM5703at Module 1 Utility area.
9) Uncoupled runs for PM1105A/B/C at Module 1 Process area.
10) Replacement of Rotary-MEC coordinator Chang (contract expired) with Angelito Bacasmot
Activities achieved for the week ending Jul8
1) Electrochlorination transformer #1 scaffolding setup, oil pumpout (manual), new & old oil dielectric test, oxidation test.
2) Transformer oil filter test run.
3) Visual status check of Module 1 motors with Asadra (Karim).
4) Receipt of MLNG drawing BTU-40.009 (master single line diagram).
5) Receipt of MarelliMotori megger resistance acceptance criteria from vendor (FKI); 10Mohm for new motors, 1Mohm for old motors. (New motors for P-1105A/B tested at 3-8Mohm.)
6) Oven heating of P-1105A/B Marellimotori units at MLNG workshop. (Motors are 2.2kW 5.2A @ 50Hz, delta connection only.)
7) Ask MLNG which substation boilers/GTGs at Module 1 feed power to, if at all.
8) Inform Asadra & inspector on MLNG’s concern about motor uncoupled run delay. Ask why the delay is occurring.
9) Inform inspector that MLNG security instructed to use the old slugcatcher pink pass instead of the MRR contractor pass given to us. Requested the old slugcatcher pink pass be returned to us.
10) Copy process description documents from Commissioning Engineer.
11) Follow-up on MLNG operations request to check PTS requirements for number of oil samples to be withdrawn from new drums.
12) Attend confined space entry HSE lecture.
13) Nitrogen filling of electrochlorination transformer #1 to reduce water ingress. (Note: transformer couldn’t be completely emptied via handpumping; i.e. the transformer oil containment base does not seem to be flat. Oil change vendor replied verbally the 200-250L old oil remaining on the transformer was not a concern because it is below the transformer core level. KBR supervisor also informed the new oil filtration shouldn’t be done at MLNG workshop but done next to the transformer while the oil is inside, using it as a breaker tank. New oil is easily contaminated during transport out to in back into drums. KBR supervisor also expressed concern the transformer’s original tapping setting was not marked by MLNG prior to removal. KBR supervisor did not approve the transformer oil change procedure for the above reasaons but was overridden by MLNG; his recommended practice was to facbricate a drain plug, drain, and cut off the transformer top head to perform a visual inspection of the core prior to rewelding back and filling with new oil & Nitrogen filling)
Activities achieved for the week ending Jun24
1) Close both verbal and official Slugcatcher III (previous project) electrical punchlist.
2) Note location of Utilities Module 1 motors to be replaced or repainted.
3) Read through electrochlorination transformer oil change procedure.
4) Introduction to MRR PMT staff Shawn Shircliffe (Buzz), Hitoshi Chikayasu, Ibrahim Siji, Aban.
5) MRR HSE induction.
6) Receipt of cabin for desk work.
7) Fill up punchcards.
1) Post overnight noload test oil sampling and dielectric test for electrochlorination transformer 4201A.
2) Overnight loaded test of transformer 4201A; tempaerature check.
3) Deenergisation of transformer 4201B.
4) Filter new oil for transformer 4201B.
5) Replace fuse & thyristor for transformer 4201A after tripping on second night of loaded operation.
6) Install new Gate Pulse Array circuit board for transformer 4201B.
7) Oil sampling and dielectric testing ofr 4201B old, new unfiltered and new filtered oil.
8) Pumpout old oil and fill-up 4201B. Post-fill oil sampling and dielectric test.
9) Re-energise 4201A and energise 4201B for no-load test.
10) Deenergise and reenergise 4201B for load test.
11) Relocate scaffolding from 4201B to 4201C
12) Apply for 4201C deenergisation.
Activities achieved for the week ending Jul15
1) New & higher flowrate transformer oil filter & enclosed 12000L breaker tank arrival onsite, scaffolding-shelter setup, safety inspection.
2) Calibration certificate & manufacturing date trace for both 3rd party & MLNG oil dielectric testers; both testers found overdue for calibration
3) Simultaneous oil degradation-comparison test for both 3rd party & MLNG oil dielectric testers (IEC156 test).
4) Electrochlorination transformer 4201A tap seal repair & tap setting check.
5) Clean/repair corroded contactor at maintenance power receptacle junction box at SS19. Power receptacle used to supply power to the transformer oil filter.
6) Cover transformer oil minor oil spills (caused by sampling) with white sand.
7) Demob of old / contaminated oil filter from electrochlorination area.
8) Uncoupled runs for PM5705A/5B, MM5703at Module 1 Utility area.
9) Uncoupled runs for PM1105A/B/C at Module 1 Process area.
10) Replacement of Rotary-MEC coordinator Chang (contract expired) with Angelito Bacasmot
Activities achieved for the week ending Jul8
1) Electrochlorination transformer #1 scaffolding setup, oil pumpout (manual), new & old oil dielectric test, oxidation test.
2) Transformer oil filter test run.
3) Visual status check of Module 1 motors with Asadra (Karim).
4) Receipt of MLNG drawing BTU-40.009 (master single line diagram).
5) Receipt of MarelliMotori megger resistance acceptance criteria from vendor (FKI); 10Mohm for new motors, 1Mohm for old motors. (New motors for P-1105A/B tested at 3-8Mohm.)
6) Oven heating of P-1105A/B Marellimotori units at MLNG workshop. (Motors are 2.2kW 5.2A @ 50Hz, delta connection only.)
7) Ask MLNG which substation boilers/GTGs at Module 1 feed power to, if at all.
8) Inform Asadra & inspector on MLNG’s concern about motor uncoupled run delay. Ask why the delay is occurring.
9) Inform inspector that MLNG security instructed to use the old slugcatcher pink pass instead of the MRR contractor pass given to us. Requested the old slugcatcher pink pass be returned to us.
10) Copy process description documents from Commissioning Engineer.
11) Follow-up on MLNG operations request to check PTS requirements for number of oil samples to be withdrawn from new drums.
12) Attend confined space entry HSE lecture.
13) Nitrogen filling of electrochlorination transformer #1 to reduce water ingress. (Note: transformer couldn’t be completely emptied via handpumping; i.e. the transformer oil containment base does not seem to be flat. Oil change vendor replied verbally the 200-250L old oil remaining on the transformer was not a concern because it is below the transformer core level. KBR supervisor also informed the new oil filtration shouldn’t be done at MLNG workshop but done next to the transformer while the oil is inside, using it as a breaker tank. New oil is easily contaminated during transport out to in back into drums. KBR supervisor also expressed concern the transformer’s original tapping setting was not marked by MLNG prior to removal. KBR supervisor did not approve the transformer oil change procedure for the above reasaons but was overridden by MLNG; his recommended practice was to facbricate a drain plug, drain, and cut off the transformer top head to perform a visual inspection of the core prior to rewelding back and filling with new oil & Nitrogen filling)
Activities achieved for the week ending Jun24
1) Close both verbal and official Slugcatcher III (previous project) electrical punchlist.
2) Note location of Utilities Module 1 motors to be replaced or repainted.
3) Read through electrochlorination transformer oil change procedure.
4) Introduction to MRR PMT staff Shawn Shircliffe (Buzz), Hitoshi Chikayasu, Ibrahim Siji, Aban.
5) MRR HSE induction.
6) Receipt of cabin for desk work.
7) Fill up punchcards.
Wednesday, July 02, 2003
MRR Module 1 electrical progress:
-electrochlorination transformer "A" barricading and sheltering
-get Rustam's (Asadra) agreement to re-megger heat trace cables after piping insulation installation per Thermion installation guide
-buy USB flashdrive to copy large process description docs from Zul's (Commissioning) PC
-get master single line diagram of MLNG plant (A1 size) from Wan Aswandi / Jalil Bujang
-visit motor workshop to witness P-1105A/B 2.2kW motors being heated in oven to remove water (motors failed megger test for coils; only 3Mohm reading; MLNG3 spec is 15Mohm minimum)
-forward SG13course/leave application forms from Naomi/En Khazin to Buzz Shircliffe's desk
-exchange phone numbers with Chan (Rotary) for witnessing of dielectric test of old and new electrochlorination transformer oil at Sesco tomorrow.
-Boiler 5130 insulation has yet to be completely removed for heat tracing cable installation. Boiler 5120 heat tracing cables have been installed, meggered and are ready for piping insulation installation.
-Read up contract scope for HV switchgear modification at SS1 and 17 (AVR & UPS upgrade)
Zul is concerned on late construction handover to his commissioning team; he only has a month left to commission Module 1 but it hasn't been handed over from construction yet.
Conversation extract with Chika today:
"Adam-san, do you know what Salim did today."
"..No. Should I?"
(frowning) "No."
"Is there anything you'd like us to do?"
(shaking head) "No."
"Well, if there's anything you'd like us to do, let us know.."
(Terminator-style) "Have a nice day."
-electrochlorination transformer "A" barricading and sheltering
-get Rustam's (Asadra) agreement to re-megger heat trace cables after piping insulation installation per Thermion installation guide
-buy USB flashdrive to copy large process description docs from Zul's (Commissioning) PC
-get master single line diagram of MLNG plant (A1 size) from Wan Aswandi / Jalil Bujang
-visit motor workshop to witness P-1105A/B 2.2kW motors being heated in oven to remove water (motors failed megger test for coils; only 3Mohm reading; MLNG3 spec is 15Mohm minimum)
-forward SG13course/leave application forms from Naomi/En Khazin to Buzz Shircliffe's desk
-exchange phone numbers with Chan (Rotary) for witnessing of dielectric test of old and new electrochlorination transformer oil at Sesco tomorrow.
-Boiler 5130 insulation has yet to be completely removed for heat tracing cable installation. Boiler 5120 heat tracing cables have been installed, meggered and are ready for piping insulation installation.
-Read up contract scope for HV switchgear modification at SS1 and 17 (AVR & UPS upgrade)
Zul is concerned on late construction handover to his commissioning team; he only has a month left to commission Module 1 but it hasn't been handed over from construction yet.
Conversation extract with Chika today:
"Adam-san, do you know what Salim did today."
"..No. Should I?"
(frowning) "No."
"Is there anything you'd like us to do?"
(shaking head) "No."
"Well, if there's anything you'd like us to do, let us know.."
(Terminator-style) "Have a nice day."